Deep Soil Mixing

Project Name: Daimonkamiike ground improvement construction, 2008

Owner Name: Urban Renaissance Agency
Main Contractor: Fudo Tetra Corporation
Construction Contents: Soil : Silty sand / Depth : 100(ft) / Volume : 945,000(ft3)
Start Date: 09/15/2009
Completion Date: 01/20/2010

Project Name: Tomakomai port Donggang ward ground improvement construction

Owner Name: Muroran Development and Construction Department
Main Contractor: Hishinaka Construction Corporation
Construction Contents: Soil : Sand / Depth : 30(ft) / Volume : 393,000(ft3)
Start Date: 10/11/2008
Completion Date: 01/09/2009

Project Name: Toyosu canal inside building a breakwater (reinforcement) construction,2008

Owner Name: Tokyo-to
Main Contractor: Tobishima Corporation
Construction Contents: Soil : Silty sand / Depth : 48(ft) / Volume : 1,060,000(ft3)
Start Date: 09/29/2008
Completion Date: 12/26/2008

Project Name: Terasaki district No.3 project leveling of ground others construction

Owner Name: Urban Renaissance Agency, Chiba
Main Contractor: Aomi Contruction CO.,LTD.
Construction Contents: Soil : Clay / Depth : 60(ft) / Volume : 1,040,000(ft3)
Start Date: 10/24/2008
Completion Date: 01/31/2009

Project Name: General National highway No. 40 Toyotomicho Kabutonuma improvement construction ground improvement

Owner Name: Wakkanai Development and Construction Department
Main Contractor: Tanaka Construction Corporation
Construction Contents: Soil : Clay, Organics / Depth : 40(ft) / Volume : 224,000(ft3)
Start Date: 12/03/2007
Completion Date: 02/20/2008

Project Name: Access road of Dououken 8, Mihara, Ebetsu-shi improvement construction ground improvement

Owner Name: Sapporo Development and Construction Department
Main Contractor: Sunagogumi Corporation
Construction Contents: Soil : Silty sand , Organics / Depth : 100(ft) / Volume : 740,000(ft3)
Start Date: 08/06/2007
Completion Date: 11/05/2007

Project Name: Access road of Dououken Toiubetu-chou Shinotsu canal north improvement construction

Owner Name: Sapporo Development and Construction Department
Main Contractor: Sunagogumi Corporation
Construction Contents: Soil : Clay, Organics / Depth : 70(ft) / Volume : 327,000(ft3)
Start Date: 04/17/2006
Completion Date: 07/28/2006

Project Name: Tohoku main line Sakae roadbed other construction Deep mixing mathod

Owner Name: Japan Railway Construction Transport and Technology Agency
Main Contractor: Fujita Corporation
Construction Contents: Soil : Sand, Clay, Organics / Depth : 28(ft) / Volume : 210,000(ft3)
Start Date: 12/26/2005
Completion Date: 04/10/2006

Project Name: Nisentei laying earth on the ground new construction between Tohoku Main Line Shinainuma / Kashimadai

Owner Name: East Japan Railway company
Main Contractor: Taisei Corporation
Construction Contents: Soil : Silty sand / Depth : 120(ft) / Volume : 810,000(ft3)
Start Date: 04/14/2006
Completion Date: 12/02/2006

Project Name: The second sharp Kameyama factory building works

Owner Name: SHARP
Main Contractor: Shimizu Corporation
Construction Contents: Soil : Clay gravel  / Depth : 26(ft) / Volume : 1,164,000(ft3)
Start Date: 02/15/2005
Completion Date: 04/08/2005

Project Name: Ground improvement with the Iwatsuki southern part Shinwa Western Division I-5-5 leveling of ground et al. construction

Owner Name: Urban Renaissance Agency
Main Contractor: Okumura Corporation
Construction Contents: Soil : Silty sand / Depth : 120(ft) / Volume : 1,540,000(ft3)
Start Date: 08/04/2005
Completion Date: 02/16/2006

Project Name: The third Okuno pumping station rainwater pump ridge work construction

Owner Name: Aomori-shi
Main Contractor: JDC Corporation
Construction Contents: Soil : Silty sand , Clay / Depth : 40(ft) / Volume : 440,000(ft3)
Start Date: 12/22/2004
Completion Date: 03/31/2005

Project Name: Evil 27 Tiyonoura fishing port disaster restoration construction, 2003

Owner Name: Kushiro construction administration
Main Contractor: Senseki Kogyo Corporation
Construction Contents: Soil : Sand / Depth : 26(ft) / Volume : 263,000(ft3)
Start Date: 04/14/2004
Completion Date: 08/23/2004

Project Name: Yoichi river repair Yoichi district No.1 project

Owner Name: Otaru construction administration
Main Contractor: Kusawake Coporation
Construction Contents: Soil : Silty Sand, Organics / Depth : 70(ft) / Volume : 230,000(ft3)
Start Date: 11/19/2002
Completion Date: 01/22/2003

Project Name: Angola LNG project

Owner Name: Angola LNG
Main Contractor: Raito Kogyo. CO., LTD
Construction Contents: Soil : Sand, Clay, Organics / Depth : 80(ft) / Volume : 21,900,000(ft3)
Start Date: 08/01/2008
Completion Date: 10/31/2009

Project Name: Kasaoka bypass steel tube district improvement construction

Owner Name: Ministry of Land, Infrastructure, Transport and Tourism, Chugoku
Main Contractor: Aomi Contruction CO.,LTD.
Construction Contents: Soil :  Silty sand / Depth : 50(ft) / Volume : 770,000(ft3)
Start Date: 12/01/2008
Completion Date: 04/30/2009

Project Name: Leveling of ground et al. construction out of 7-42 South Chiba district blocks

Owner Name: Urban Renaissance Agency, Chiba
Main Contractor: Shimizu Corporation
Construction Contents: Soil : Clay, Organics / Depth : 46(ft) / Volume : 775,000(ft3)
Start Date: 12/01/2008
Completion Date: 04/30/2009

Project Name: Kise Expressway Tayama construction

Owner Name: Central Nippon Expressway Company Limited
Main Contractor: Aomi Contruction CO.,LTD.
Construction Contents: Soil : Silty sand / Depth : 46(ft) / Volume : 775,000(ft3)
Start Date: 01/01/2009
Completion Date: 06/30/2009

Project Name: Hitachi Nasu thermal power station No.2 enlargement construction

Owner Name: The Tokyo Electric Power Company, Inc
Main Contractor: Chemical Grouting CO.,LTD
Construction Contents: Soil : Common fill, Sand / Depth : 37(ft) / Volume : 2,360,000(ft3)
Start Date: 09/01/2009
Completion Date: 02/28/2010

Project Name: Hirono thermal power station No.6 enlargement construction

Owner Name: The Tokyo Electric Power Company, Inc
Main Contractor: Shimizu Corporation
Construction Contents: Soil : Silt / Depth : 35(ft) / Volume : 3,700,000(ft3)
Start Date: 10/01/2009
Completion Date: 02/28/2010